Trial synchronisation may initially feed 300–400MW into the grid as authorities assess system stability ahead of commercial generation.
An aerial overview of Bangladesh’s first Rooppur Nuclear Power Plant showing its reactor units and cooling towers. Photo: Courtesy
“>
An aerial overview of Bangladesh’s first Rooppur Nuclear Power Plant showing its reactor units and cooling towers. Photo: Courtesy
The Rooppur Nuclear Power Plant (RNPP) is likely to connect to the national grid for the first time on a trial basis tomorrow (17 November), marking a major step in testing the country’s first nuclear power facility.
The trial synchronisation will assess how electricity generated by the plant is transferred to the national grid and how the power system responds to the additional supply, particularly its ability to maintain stable frequency.
Md Rezaul Karim, chairman of the Bangladesh Power Development Board (BPDB), said he had been informed by the RNPP project director that preparations were underway to connect the plant to the grid.
“I have been informed by the project director of Rooppur Nuclear Power Plant that it would be connected to the national grid by tomorrow,” he said.
A Power Grid Bangladesh PLC (PGB) official, however, said several previous attempts to synchronise the plant with the grid had been unsuccessful.
“There is an attempt scheduled, and it is likely to happen. But I cannot say for certain when it will take place. It will happen very soon,” the official said, requesting that the matter be handled sensitively.
The plant may initially supply around 300–400MW to the national grid, according to the RNPP authorities.
Md Anwar Hossain, secretary of the Ministry of Science and Technology, said the synchronisation would be part of the plant’s testing programme, as it was now ready to transfer generated electricity to the grid.
“Connecting with the power grid is part of a larger test to assess how the national grid behaves when electricity from the nuclear plant is injected into it, particularly whether the system can maintain a stable frequency,” he said.
He said adjustments to the turbine had been completed and the next step was to observe how the grid responds when electricity is supplied.
“Ultimately, the plant has to be connected with the grid. The adjustments to the turbine have been completed. When it is connected to the grid, we will observe how the grid behaves, what happens to the frequency and whether the system remains stable,” he added.
The plant will remain connected for a certain period before being shut down for further observation, a process the authorities described as a normal part of commissioning.
“After connecting it, they will observe it for some time and then shut it down again and check. These are normal procedures,” Anwar Hossain said.
He said the plant could continue operating for a few hours if the initial synchronisation proved successful and the grid remained stable. However, any technical challenge would require an immediate shutdown.
“If everything works well and the system remains stable, it may run for a few hours. If any challenge arises, it will be shut down immediately. Then it may be connected again,” he said.
An official familiar with the project said several more tests would be conducted before the plant could move towards commercial electricity generation.
“This is one of the tests. Along with this, around nine more tests will be conducted. If the collaboration works properly, another six tests will follow. After completing all these tests, we will finally move towards commercial electricity generation,” the official said, requesting anonymity.
Anwar Hossain described the grid synchronisation as the first attempt to transfer electricity from the plant to the national grid.
“Technically, our generation-side work is ready. Now, after generating electricity, we have to evacuate it. This evacuation is what we call grid synchronisation. This is the first time we are attempting it,” he said.
Bangladesh’s first nuclear power facility has a total gross generation capacity of 2,400MW across two reactors. It is equipped with Russian Generation III+ VVER-1200 reactors, each with a gross capacity of 1,200MW.
Construction began with the first concrete pour for Unit 1 on 30 November 2017 and for Unit 2 on 14 July 2018.
Owned by the Bangladesh Atomic Energy Commission and built by Russia’s Rosatom under an initial agreement worth $12.65 billion, the project is 90% funded through Russian state credit.