The Power Division has already provisionally shortlisted 8,236 firms nationwide to execute the projects.
Infograph: TBS
“>
Infograph: TBS
Public institutions will receive 10% of the electricity generated from rooftop solar panels installed on their buildings free of charge as “roof rent”, while private investors will retain the remaining 90% to sell back to the host offices or the national grid under a proposed government policy.
If a host institution consumes more than its free 10% share, it will buy the extra solar power from the private operator at a 20% discount on the applicable government-approved retail tariff.
Prepared by the Power Division, the draft policy aims to accelerate green energy adoption across government, semi-government, autonomous, and local government bodies, as well as state-owned enterprises, without requiring upfront state funding.
Under the framework, enlisted private firms will finance, install, and maintain the solar systems for 15 years under an operational expenditure (Opex) model. Alternatively, financially independent public bodies can fund their own installations under a capital expenditure (Capex) model.
The Power Division has already provisionally shortlisted 8,236 firms nationwide to execute the projects, with a final list pending payment of registration fees.
Cabinet review and procurement exemptions
The draft policy was discussed at a cabinet meeting chaired by Prime Minister Tarique Rahman on 12 October. The cabinet instructed the Power Division to review the proposal with the law ministry to ensure alignment with the Public Procurement Act, the Electricity Act, and the Invest Bangladesh Act before resubmitting it for final approval.
Infograph: TBS
“>
Infograph: TBS
According to cabinet meeting minutes, the Power Division simplified enlistment rules to shortlist a set number of investors per district. Because no government funds are spent under the Opex model, public institutions can competitively select providers from this roster without triggering standard Public Procurement Act restrictions.
However, the division is seeking swift clearance so that revenue-generating state bodies can also use the same enlisted firms for self-funded Capex installations.
Special tariffs and payment structure
To balance commercial viability for investors with savings for public entities, the draft sets specific tariff rules for power consumed beyond the free 10% allocation.
The applicable tariff for educational, religious and charitable institutions, as well as hospitals in the LT-D1 category (up to 400 volts), will be Tk8.50 per unit, compared with the existing retail rate of Tk9.05.
For other institutions, the payment to service providers for electricity consumed beyond the free allocation will be calculated at 80% of the applicable retail tariff.
General government offices under the LT-E category pay Tk13.82 per unit for daytime electricity. At 80% of this tariff, operators will earn over Tk11 per unit.
For large government offices or complexes under the MT-2 category, currently pay Tk12.54 per unit during daytime/off-peak hours, yielding operators more than Tk10.
Energy economist Shafiqul Alam told TBS that the pricing offers strong incentives for Opex companies, allowing them to earn roughly Tk10 per unit while sparing public offices the technical burden of running solar plants. However, industry insiders note that some private factories are already securing Opex solar installations at lower tariffs than those proposed for the public sector.
Procurement rule changes for self-funded projects
For institutions opting for the self-funded Capex model, which allows them to earn revenue by exporting surplus power to the grid, the Power Division has proposed several regulatory adjustments:
- Higher tendering limits: Raising the financial ceiling under the Limited Tendering Method from Tk50 lakh to Tk5 crore, depending on equipment specs and battery inclusion.
- Mandatory battery storage: Requiring systems exceeding 25 kilowatt-peak (kWp) to include battery storage equivalent to at least 20% of their rated capacity.
- Longer agreements: Extending the maximum framework agreement period under the Public Procurement Act from three years to 15 years to match the mandatory maintenance window.
- e-GP exemption: Bypassing mandatory electronic government procurement (e-GP) procedures to fast-track installations ahead of a February incentive deadline.
4,000MW target by February 2027
The initiative underpins the National Renewable Energy Development Strategy 2026–2030, which targets 3,000–4,000MW of rooftop solar capacity by February 2027.
To meet this deadline, the government has introduced an incentive under its net metering guidelines: consumers who install systems by 28 February 2027 and feed surplus electricity into the national grid will receive Tk10.50 per unit for three years.
Under the proposed tripartite agreements—signed between the building owner, the investor, and the power distribution utility—generated solar power will first meet the host building’s demand before exporting any surplus. Distribution utilities will charge a nominal Tk0.05 per unit to meter the grid-solar split, adjust government incentives, and settle final payments with the private operators.
Experts flag maintenance risks
Shafiqul Alam noted that the Opex model is far more practical for public offices whose core mandates lie outside energy management, and will be critical to meeting Bangladesh’s target of generating 20% of its electricity from renewables by 2030.
However, he warned that the government must vet whether the 8,236 shortlisted firms actually possess the engineering capacity, installers, and maintenance crews required for a 15-year commitment.
“Regular cleaning and upkeep are essential due to heavy dust in the air,” Islam said, cautioning that neglected panels can lose around 4% of their generation efficiency every year.