The Executive Committee of the National Economic Council (Ecnec) has approved seven projects worth Tk20,441 crore to develop local infrastructure ahead of the local government elections.
The projects, under the local government, rural development and cooperatives ministry, include five new schemes and two revised ones. They place particular emphasis on building long bridges in rural areas, improving roads and infrastructure in several districts, and strengthening Dhaka’s sewage management system.
The projects were approved at an Ecnec meeting held at the Bangladesh Secretariat today (18 November), chaired by Prime Minister and Ecnec Chairperson Tarique Rahman.
Including these projects, Ecnec approved a total of 16 new and revised projects worth Tk33,298.48 crore at the meeting.
With local government elections planned from January, the government is placing particular emphasis on development activities in rural areas. Through these projects, it aims to improve rural connectivity, stimulate local economies and create employment opportunities.
Among the approved schemes, the largest allocation has been earmarked for constructing long bridges on upazila, union and village roads.
The project, being implemented by the Local Government Engineering Department (LGED), has an estimated cost of Tk8,888.38 crore. Fully funded by the government, it is scheduled for completion by June 2031.
According to the project proposal, the government plans to construct 256 long bridges in 48 districts to improve rural connectivity. The bridges will have a combined length of 49,050 metres.
The initiative aims to improve road access to rural markets, industrial establishments, agricultural production centres, river terminals, healthcare facilities and educational institutions. The bridges are expected to improve connectivity in areas where the lack of long bridges has disrupted direct communication, while reducing travel time and transportation costs for goods.
In addition to the bridges, the project includes protective works for 7,700 metres of existing bridges and the construction of 65.187 kilometres of connecting roads.
Another project, worth Tk5,106 crore, has been approved to develop rural infrastructure in four districts of the Sylhet division — Sylhet, Sunamganj, Moulvibazar and Habiganj. The project will be fully funded by the government and is scheduled to run until September 2030.
A new project has also been approved to develop key rural infrastructure in Faridpur and Rajbari districts, at an estimated cost of Tk2,817.72 crore. LGED will implement the project with full government funding by December 2030.
Under the project, 1,565.36 kilometres of earthen roads will be paved across 14 upazilas in the two districts.
Ecnec also approved the first revision of a rural infrastructure development project in Joypurhat district. The project cost has been increased to Tk831.66 crore from Tk499.90 crore. Launched in January 2024, it is scheduled for completion by December 2028.
Meanwhile, a new project worth Tk2,199 crore has been taken up to develop rural infrastructure in the Jessore region. LGED will implement it by December 2029.
The project will develop climate-resilient rural infrastructure and market services in 21 upazilas across four districts of the Khulna division — Jessore, Jhenaidah, Magura and Narail.
Ecnec also approved the second revision of the third phase of the Rural Livelihood Project, aimed at improving the livelihoods of rural communities. The project, implemented by the Bangladesh Rural Development Board (BRDB), will now cost Tk1,061.45 crore, up from Tk955.46 crore. The project will cover 249 upazilas in 52 districts across all eight divisions.
An interim evaluation of the project also recommended extending its activities over a longer period. Accordingly, a two-year extension has been proposed to achieve its objectives and expand operations into the new areas.
Dhaka sewage management
Meanwhile, Ecnec approved a project to construct sewage collection lines for the Dasherkandi Sewage Treatment Plant to improve wastewater management in the capital. The project, to be implemented by Dhaka WASA, will cost Tk993.64 crore.
The government plans to divert sewage from Gulshan, Banani and Baridhara to the Dasherkandi treatment plant instead of allowing it to flow into lakes, canals and other water bodies. To this end, 140 kilometres of sewage lines will be constructed.
Other projects approved
Four projects under the water resources ministry received approval. One of them, aimed at improving drainage and irrigation facilities through the excavation and re-excavation of canals, small rivers and water bodies across the country, has an estimated cost of Tk6,922 crore. Several other projects were also approved to tackle river erosion.
Two projects under the Road Transport and Highways Division were approved. One of them will upgrade the Mokamtala-Kalai-Joypurhat regional highway into a four-lane road with service lanes at a cost of Tk1,937 crore. Another project will develop highways under the Joypurhat Road Division.
The agriculture ministry’s small-scale irrigation development project for Joypurhat, Bogura and Gaibandha districts also received approval.
Other approved schemes include the construction of a training centre for the National Security Intelligence agency in Dhamrai, Dhaka, under the Prime Minister’s Office, and an infrastructure development project to address housing shortages for Bangladesh Air Force officers in the Dhaka area, under the defence ministry.