The first unit began supplying 350MW of electricity to the national grid for the first time at 3pm today.
Rooppur Nuclear Power Plant. Photo: TBS/File
“>
Rooppur Nuclear Power Plant. Photo: TBS/File
After a long wait, extensive technical work and a series of complex tests, electricity generated by Rooppur Nuclear Power Plant has been connected to the national grid on a trial basis.
The first unit began supplying 350MW of electricity to the national grid for the first time at 3pm today (17 November), in the presence of Science and Technology Minister Faqir Mahbub Anam.
More to follow…